Project Description

We were asked by a local cheese factory to upgrade there supply to site due to expansion.  We provided them a full turnkey solution this involved us arranging the local DNO to install a new HV ring main and 1000kva transformer.  We then upgraded there main section board and PFC so it was capable of handling there new supply.  We provided them with temporary generators so their business was not disrupted for the 2 weeks they were  without power.